Critical Path Method Analysis PMP Exam Quiz

Welcome to your Critical Path Method Quiz!

1. 
A technique that calculates early start and early finish dates in the schedule network

2. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?

3. 
A project can have more than one critical path

4. 
Who decides Mandatory and Discretionary Dependencies?

5. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?

6. 
The longest path in a project schedule network diagram is called

7. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called

8. 
Critical Path Method uses deterministic (single point) activity time estimates

9. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called

10. 
Improper use of which of the following may result in arbitrary total float.

11. 
Critical Path Method establishes the minimum project duration

12. 
Who decides Internal and External Dependencies?

13. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)

14. 
Total float of activities on critical path is usually zero.

15. 
Critical Path Method controls both time and cost aspect of a project

16. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method

Add description here!

17. 
For activities on critical path Early Start is equal to

18. 
In scheduling software Lag is often represented using a negative value

19. 
An activity that comes after a dependent activity in a project schedule is called?

20. 
A technique that calculates late start and late finish dates in the schedule network is called

21. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called

22. 
Discretionary Dependencies are also known as

23. 
Mandatory Dependencies are also known as

24. 
An activity that comes before a dependent activity in a project schedule is called?

25. 
An activity on critical path is called

26. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called

27. 
In scheduling software Lead is often represented using a positive value

28. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called

29. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called

30. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?


Discover more from MilestoneTask

Subscribe to get the latest posts sent to your email.

34 thoughts on “Critical Path Method Analysis PMP Exam Quiz

  1. 15. Discretionary Dependencies are also known as ( Please RECTIFY this anwser.

    ** Soft Logic
    Internal Dependencies
    External Dependencies
    Hard Logic