Critical Path Method PMP Exam Questions

Critical Path Method PMP Quiz

Welcome to your Critical Path Method Quiz!

email
Name
1. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called

2. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called

3. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called

4. 
A technique that calculates early start and early finish dates in the schedule network

5. 
Discretionary Dependencies are also known as

6. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?

7. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?

8. 
Improper use of which of the following may result in arbitrary total float.

9. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method

Add description here!

10. 
Who decides Mandatory and Discretionary Dependencies?

11. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called

12. 
An activity that comes after a dependent activity in a project schedule is called?

13. 
A project can have more than one critical path

14. 
Total float of activities on critical path is usually zero.

15. 
A technique that calculates late start and late finish dates in the schedule network is called

16. 
Mandatory Dependencies are also known as

17. 
An activity on critical path is called

18. 
Critical Path Method uses deterministic (single point) activity time estimates

19. 
Critical Path Method establishes the minimum project duration

20. 
An activity that comes before a dependent activity in a project schedule is called?

21. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called

22. 
Critical Path Method controls both time and cost aspect of a project

23. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called

24. 
Who decides Internal and External Dependencies?

25. 
The longest path in a project schedule network diagram is called

26. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)

27. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?

28. 
In scheduling software Lead is often represented using a positive value

29. 
For activities on critical path Early Start is equal to

30. 
In scheduling software Lag is often represented using a negative value