Critical Path Method PMP Exam Questions

Critical Path Method PMP Quiz

Welcome to your Critical Path Method Quiz!

email
Name
1. 
An activity that comes before a dependent activity in a project schedule is called?
2. 
A technique that calculates late start and late finish dates in the schedule network is called
3. 
Who decides Internal and External Dependencies?
4. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method
Add description here!
5. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?
6. 
An activity that comes after a dependent activity in a project schedule is called?
7. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called
8. 
Critical Path Method uses deterministic (single point) activity time estimates
9. 
Critical Path Method establishes the minimum project duration
10. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?
11. 
For activities on critical path Early Start is equal to
12. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called
13. 
Total float of activities on critical path is usually zero.
14. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)
15. 
In scheduling software Lead is often represented using a positive value
16. 
Who decides Mandatory and Discretionary Dependencies?
17. 
Improper use of which of the following may result in arbitrary total float.
18. 
Critical Path Method controls both time and cost aspect of a project
19. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called
20. 
A technique that calculates early start and early finish dates in the schedule network
21. 
The longest path in a project schedule network diagram is called
22. 
An activity on critical path is called
23. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?
24. 
A project can have more than one critical path
25. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called
26. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called
27. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called
28. 
Discretionary Dependencies are also known as
29. 
Mandatory Dependencies are also known as
30. 
In scheduling software Lag is often represented using a negative value