1.
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?
2.
In scheduling software Lead is often represented using a positive value
3.
A technique that calculates early start and early finish dates in the schedule network
4.
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called
5.
Which of these activity relationships is most commonly used in Precedence Diagramming Method?
6.
For activities on critical path Early Start is equal to
7.
The longest path in a project schedule network diagram is called
8.
Amount of time that a successor activity can be advanced with respect to its predecessor is called
9.
Critical Path Method establishes the minimum project duration
10.
Total float of activities on critical path is usually zero.
11.
Discretionary Dependencies are also known as
12.
Amount of time that a successor activity can be delayed with respect to its predecessor is called
13.
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)
14.
Which of these activity relationships is least commonly used in Precedence Diagramming Method
15.
An activity that comes after a dependent activity in a project schedule is called?
16.
Critical Path Method uses deterministic (single point) activity time estimates
17.
The critical path method analysis uses which of the following techniques to create a schedule network digram?
18.
Improper use of which of the following may result in arbitrary total float.
19.
An activity that comes before a dependent activity in a project schedule is called?
20.
A project can have more than one critical path
21.
Mandatory Dependencies are also known as
22.
Critical Path Method controls both time and cost aspect of a project
23.
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called
24.
A technique that calculates late start and late finish dates in the schedule network is called
25.
In scheduling software Lag is often represented using a negative value
26.
Who decides Internal and External Dependencies?
27.
Who decides Mandatory and Discretionary Dependencies?
28.
An activity on critical path is called
29.
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called
30.
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called
according to me keep It up, like it
Thanks for the appreciation
15. Discretionary Dependencies are also known as ( Please RECTIFY this anwser.
** Soft Logic
Internal Dependencies
External Dependencies
Hard Logic
Thanks for pointing it out
How do I access the questions? All I see is the header image and comments.
Hi, Thanks for pointing it out. The issue is now fixed. Both the quizzes are working.
Solving these questions made my concepts more clear
Thank You!
good exercise
Thank You!
wow excellent exercise.
Thanks
Thank you
test
Great
Thank You!
good exercise
Thank You!