Critical Path Method Analysis PMP Exam Quiz

Welcome to your Critical Path Method Quiz!

1. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called

2. 
An activity on critical path is called

3. 
In scheduling software Lead is often represented using a positive value

4. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called

5. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?

6. 
Who decides Mandatory and Discretionary Dependencies?

7. 
An activity that comes before a dependent activity in a project schedule is called?

8. 
A technique that calculates early start and early finish dates in the schedule network

9. 
Total float of activities on critical path is usually zero.

10. 
An activity that comes after a dependent activity in a project schedule is called?

11. 
For activities on critical path Early Start is equal to

12. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method

Add description here!

13. 
Critical Path Method establishes the minimum project duration

14. 
The longest path in a project schedule network diagram is called

15. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called

16. 
A technique that calculates late start and late finish dates in the schedule network is called

17. 
Critical Path Method uses deterministic (single point) activity time estimates

18. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called

19. 
Improper use of which of the following may result in arbitrary total float.

20. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?

21. 
A project can have more than one critical path

22. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called

23. 
Who decides Internal and External Dependencies?

24. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?

25. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)

26. 
Mandatory Dependencies are also known as

27. 
Discretionary Dependencies are also known as

28. 
Critical Path Method controls both time and cost aspect of a project

29. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called

30. 
In scheduling software Lag is often represented using a negative value


Discover more from MilestoneTask

Subscribe to get the latest posts sent to your email.

34 thoughts on “Critical Path Method Analysis PMP Exam Quiz

  1. 15. Discretionary Dependencies are also known as ( Please RECTIFY this anwser.

    ** Soft Logic
    Internal Dependencies
    External Dependencies
    Hard Logic