Critical Path Method Analysis PMP Exam Quiz

Welcome to your Critical Path Method Quiz!

1. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?

2. 
For activities on critical path Early Start is equal to

3. 
An activity that comes after a dependent activity in a project schedule is called?

4. 
Critical Path Method controls both time and cost aspect of a project

5. 
Mandatory Dependencies are also known as

6. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called

7. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)

8. 
An activity that comes before a dependent activity in a project schedule is called?

9. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called

10. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method

Add description here!

11. 
Improper use of which of the following may result in arbitrary total float.

12. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called

13. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?

14. 
Who decides Internal and External Dependencies?

15. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?

16. 
In scheduling software Lead is often represented using a positive value

17. 
A technique that calculates early start and early finish dates in the schedule network

18. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called

19. 
A technique that calculates late start and late finish dates in the schedule network is called

20. 
Critical Path Method establishes the minimum project duration

21. 
Who decides Mandatory and Discretionary Dependencies?

22. 
Total float of activities on critical path is usually zero.

23. 
Critical Path Method uses deterministic (single point) activity time estimates

24. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called

25. 
In scheduling software Lag is often represented using a negative value

26. 
The longest path in a project schedule network diagram is called

27. 
Discretionary Dependencies are also known as

28. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called

29. 
An activity on critical path is called

30. 
A project can have more than one critical path


Discover more from MilestoneTask

Subscribe to get the latest posts sent to your email.

34 thoughts on “Critical Path Method Analysis PMP Exam Quiz

  1. 15. Discretionary Dependencies are also known as ( Please RECTIFY this anwser.

    ** Soft Logic
    Internal Dependencies
    External Dependencies
    Hard Logic

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.