Critical Path Method Analysis PMP Exam Quiz

Welcome to your Critical Path Method Quiz!

1. 
Which of the following technique is most commonly used by project management software to construct the schedule network diagram?

2. 
In scheduling software Lead is often represented using a positive value

3. 
A technique that calculates early start and early finish dates in the schedule network

4. 
Logical relationship in which a successor activity cannot start until a predecessor activity has started is called

5. 
Which of these activity relationships is most commonly used in Precedence Diagramming Method?

6. 
For activities on critical path Early Start is equal to

7. 
The longest path in a project schedule network diagram is called

8. 
Amount of time that a successor activity can be advanced with respect to its predecessor is called

9. 
Critical Path Method establishes the minimum project duration

10. 
Total float of activities on critical path is usually zero.

11. 
Discretionary Dependencies are also known as

12. 
Amount of time that a successor activity can be delayed with respect to its predecessor is called

13. 
Which of these schedule network logic technique is an example of Precedence Diagramming Method (PDM)

14. 
Which of these activity relationships is least commonly used in Precedence Diagramming Method

Add description here!

15. 
An activity that comes after a dependent activity in a project schedule is called?

16. 
Critical Path Method uses deterministic (single point) activity time estimates

17. 
The critical path method analysis uses which of the following techniques to create a schedule network digram?

18. 
Improper use of which of the following may result in arbitrary total float.

19. 
An activity that comes before a dependent activity in a project schedule is called?

20. 
A project can have more than one critical path

21. 
Mandatory Dependencies are also known as

22. 
Critical Path Method controls both time and cost aspect of a project

23. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has started is called

24. 
A technique that calculates late start and late finish dates in the schedule network is called

25. 
In scheduling software Lag is often represented using a negative value

26. 
Who decides Internal and External Dependencies?

27. 
Who decides Mandatory and Discretionary Dependencies?

28. 
An activity on critical path is called

29. 
Logical relationship in which a successor activity cannot start until a predecessor activity has finished is called

30. 
Logical relationship in which a successor activity cannot finish until a predecessor activity has finished is called


Discover more from MilestoneTask

Subscribe to get the latest posts sent to your email.

34 thoughts on “Critical Path Method Analysis PMP Exam Quiz

  1. 15. Discretionary Dependencies are also known as ( Please RECTIFY this anwser.

    ** Soft Logic
    Internal Dependencies
    External Dependencies
    Hard Logic